ESI received a total of 89 proposals in response to the Fall 2004 RFP.
|
  |
ESI has concluded its review and evaluation of the proposals submitted in response to the Fall 2004 RFP.
|
  |
As a result of the evaluation of the "Into Entergy" LD product proposals, ESI has executed a Definitive Agreement for one (1) "Into Entergy" LD Product representing a total of 100 MW.
|
  |
As a result of the evaluation of MUCCO and MUCPA product proposals, ESI has executed the following Definitive Agreements:
|
|   |
Two (2) Day Ahead MUCCO proposals, totaling 300 MW
|
|   |
Three (3) Intra-Day Peaking MUCCO proposals, totaling 360 MW
|
|   |
One (1) Dispatchable MUCPA proposal, totaling 290 MW
|
|   |
One (1) Three-year Reserve Capacity MUCCO proposal, up to 700 MW
|
  |
Remaining Bidders have been advised that their proposals are no longer being considered.
|