ESI's Summer 2009 Long-Term RFP Request

                          For Proposals (RFP) for Supply-Side Resources
   


Thank you for your interest in
ESI’s Summer 2009 Long-Term RFP.
 

 

Final Results for the Summer 2009 RFP - Revised

ESI has concluded its review and evaluation of the proposals submitted in response to the Summer 2009 RFP and has reported the results of the review and evaluation to the Operating Committee.  ESI has received Entergy Operating Committee approval to move forward with five resources:

·         four acquisition proposals totaling approximately 2,800 MW, including the Ninemile self build option identified in the RFP; and

·         one PPA proposal totaling approximately 500 MW.

Subsequent to the RFP selections, one of the acquisition proposals that had been selected for award was withdrawn by the bidder.  Nonetheless, even with the withdrawal of this acquisition proposal, the 1,550 MW of resource needs identified when the RFP was issued have been filled.

The Independent Monitor for ESI’s Summer 2009 Long-Term RFP, Potomac Economics, has certified that the evaluation and analysis of the RFP proposals were fair and impartial, did not unfairly favor any proposal, including the self-build proposal, and were free from affiliate abuse.  In addition, the IM has certified that the various processes established under the RFP to ensure protection of confidential information were followed accordingly.  Further, the Independent Monitor has affirmed that the Operating Committee’s resource selection is consistent with the RFP evaluation results.

ESI, on behalf of the Entergy Operating Companies, will be entering into discussions for the execution of definitive agreements associated with the selected proposals.  All transactions will be contingent upon obtaining necessary regulatory approvals, including full cost recovery.

 

 

Please periodically check the website for further updates


Ask the RFP Administrator a question

Note: All of the following documents are in Adobe Acrobat, Microsoft Word or Microsoft Power Point format as indicated.

Summer 2009 RFP Main Document

Appendix A - Glossary

Appendix B - Illustration of the RFP Web Portal for the
Bidder Registration, Confirmation, and Proposal Submission Process

  Appendix C - Product Packages:  

Appendix D - Detailed Instructions for Bidder Registration and Proposal Submission

  Appendix E - Evaluation Process Description:  

Appendix F - Credit/Collateral Requirements

Appendix G - Process for Protection of Proposal Information

Appendix H - Clarifying Questions for CCGT Developmental Resources

Appendix I-1 - Preliminary Due Diligence List for Existing CCGT/CT Resources

Appendix I-2 - Preliminary Due Diligence List for Existing Solid Fuel Resources

Redline versions of these documents
Questions and Answers
 Recent Questions And Answers (Updated 11/05/2009)

Proposal Submission Agreement

Confidentiality Agreement


Summer 2009 RFP Bidders' Conference Presentation
Summer 2009 RFP Instructions for Bidder Registration and Proposal Submission

LPSC Staff’s Comments to the Draft Summer 2009 RFP (09-15-09)
ESI Response to LPSC Staff Comments (10-08-09)
Evaluation Statement Regarding Acadia Power Block 2
Notice of Delay in the Summer 2009 RFP
Independent Monitoring Report - Summer 2009 Long-Term RFP

RFP IM Scope

Affiliate Rules Compliance

Final Results for the Summer 2009 RFP - original
Notice of Change in RFP Administrator
Notice of Delay in the Summer 2009 Long-Term RFP
Evaluation Statement Regarding Acadia Power Block 2
Summer 2009 Notice Of Request For Proposals
Summer 2009 RFP Schedule
Notice of Summer 2009 RFP
Clarifying Questions for CCGT Developmental Resources

 

 

 

Return

Click here to send Questions, Comments or Suggestions.
Should you experience any difficulties in accessing this data, please contact your local IS support group.
Content Provider: ESI RFP Admin (esirfp1@entergy.com)