February 20, 2025

Notice of Schedule Update - ELL 3 GW Solar RFP

Entergy Louisiana, LLC (“ELL”) hereby notifies interested parties that the schedule for Procurement Windows 2, 3,
and 4 of the ELL 3 GW Solar RFP has changed. The updated schedule is shown below. Questions may be submitted
to the Bid Event Coordinator at ellrfp@entergy.com. Thank you for your interest in the RFP.

RFP MilestoneMilestone Date
Procurement
Window 2
Procurement
Window 3
Procurement
Window 4
Bidder Regisration Period*8:00 a.m. CPT
March 3, 2025
to 5:00 p.m. CPT
March 7, 2025
8:00 a.m. CPT
July 28, 2025
to 5:00 p.m. CPT
August 1, 2025
8:00 a.m. CPT
January 5, 2026
to 5:00 p.m. CPT
January 9, 2026
Proposal Submission Fee Payment Deadline*5:00 p.m. CPT
March 28, 2025
5:00 p.m. CPT
August 22, 2025
5:00 p.m. CPT
January 30, 2026
Self-Build Option Proposal Submission Period*8:00 a.m. CPT
April 7, 2025
to 5:00 p.m. CPT
April 11, 2025
8:00 a.m. CPT
September 8, 2025
to 5:00 p.m. CPT
September 12, 2025
8:00 a.m. CPT
February 9, 2026
to 5:00 p.m. CPT
February 13, 2026
Proposal Submission Period*(other than for Self-Build Option Proposals)8:00 a.m. CPT
April 14, 2025
to 5:00 p.m. CPT
April 18, 2025
8:00 a.m. CPT
September 15, 2025
to 5:00 p.m. CPT
September 19, 2025
8:00 a.m. CPT
February 16, 2026
to 5:00 p.m. CPT
February 20, 2026
Selections Announced*June 23, 2025November 20, 2025April 24, 2026
Definitive Agreement Negotiations Begin*July 2, 2025December 3, 2025May 4, 2026
PPABOTPPABOTPPABOT
Definitive Agreements Executed*1December
2025
March
2026
May
2026
July
2026
November
2026
February
2027
Regulatory Approval Process Complete*May
2026
August
2026
October
2026
December
2026
April
2027
July
2027

(*) - Target dates subject to change.
(1) - The time required to negotiate and execute Definitive Agreements typically varies by transaction type and depends upon numerous other factors. Similarly, the date on which the regulatory approval process concludes for a transaction turns on the execution date of the Definitive Agreement, the amount of docket congestion, and other circumstances that can differ materially from transaction to transaction and Procurement Window to Procurement Window.