January 18, 2023
2022 EML Fall Renewables RFP
Notice of Self-Build Option Proposal Submission Period - Schedule Update
The Self-Build Option Proposal Submission Period has been extended from January 26, 2023, to January 29, 2023
The schedule per the Main Body Section 4, has been updated as follows (red indicates change from prior schedule)
RFP Milestone | Milestone Date* |
---|---|
Bidders Conference | December 6, 2022 |
Bidder Registration Period | 8:00 a.m. CPT on January 3, 2023, until 5:00 p.m. CPT on January 20, 2023 |
Proposal Submission Fee Payment Deadline | 5:00 p.m. CPT on February 1, 2023 |
Self-Build Option Proposal Submission Period | 8:00 a.m. CPT on January 24, 2023,until 5:00 p.m. CPT on January 29, 2023 |
Proposal Submission Period (for all proposals other than for Self-Build Options) |
8:00 a.m. CPT on January 30, 2023,until 5:00 p.m. CPT on February 2, 2023 |
Updated Pricing for Phase 1 2021 MISO SouthDPP Queue | 5:00 p.m. CPT on February 16, 2023 |
Primary/Secondary Selections Announced | April 2023 |
Due Diligence and Negotiations Begin | April 2023 |
Definitive Agreements Executed | June 2023 |
Regulatory Approval Process Complete | November 2023 |
Questions can be submitted to the Bid Event Coordinator, copying the IM, at their respective email addresses referenced above, throughout the Bidder Registration Period. Please review Section 6 of the Main Body of the RFP before submitting any questions. Terms used but not defined in this notice have the meaning ascribed to them in the 2022 EML Fall Renewables RFP.
Please monitor the RFP website for further information. Thank you for your interest in the RFP